| Enewsletter
Panel Releases Long-Anticipated Mackenzie Gas Project Report
Implement all 176 conditions before approving Project, says Nature Canada The future of the mighty Mackenzie River – and the "basin-opening" pipeline megaproject that threatens to forever change it – has become clearer with the release of a long-anticipated environmental assessment report. A Joint Review Panel, tasked by the government to report on the environmental, socio-economic and cultural effects of the Mackenzie Gas Project, released its findings December 30, 2009, over two years after the panel's hearings ended in 2007. The panel concluded that if all of its 176 recommendations were fully implemented, the project would likely be beneficial and have no significant adverse impacts. Nature Canada has argued publicly that the National Energy Board should obtain firm, funded commitments from the federal and territorial governments to implement the recommendations of the Joint Review Panel of the Mackenzie Gas Project before approving it. "Ninety of the recommendations require action by the federal government, and fifty more require action by the Northwest Territories government. Nature Canada is skeptical that many will actually be funded and implemented without clear, enforceable direction from the National Energy Board," said Nature Canada Executive Director Ian Davidson. "The costs to the federal government alone in implementing the recommendations could run to hundreds of millions of dollars." "It is regrettable that the Panel did not simply state more clearly that the Mackenzie Gas Project is unsustainable unless governments and the proponents make a huge conservation effort," said Carla Sbert, Nature Canada's manager of conservation programs. "Now it is up to the National Energy Board to ensure that it gets solid commitments from governments that they will implement their Panel recommendations before the NEB approves construction." Nature Canada is pleased that the Joint Review Panel used a test of sustainability to assess the environmental and other impacts of the Mackenzie Gas Project. Many of the specific recommendations in the report are also welcome. "The Panel put the six globally and one continentally significant Important Bird Areas (IBAs) in the Mackenzie watershed on the map," Sbert added. "Bird-lovers everywhere should be delighted by the fact that the Panel accepted Nature Canada's recommendation that these IBA sites — which include key breeding and staging areas from Great Slave Lake to the Mackenzie Delta — should be protected under the Northwest Territories Protected Areas Strategy (NWTPAS)." Unfortunately, the Panel misunderstood the application of the NWTPAS to these Important Bird Areas and did not explicitly endorse Nature Canada's recommendations that construction-related activity in and near IBAs be limited to the October 30 to May 1 period (when migratory birds are not present), and that the physical footprint of pipeline facilities in IBAs be minimized. Nature Canada will ask the National Energy Board to make our recommendations explicit conditions in any license it issues. The Panel made other important recommendations that would protect birds and bird habitat if they are implemented by governments:
The Mackenzie Gas Project is expected to cost at least $16 billion, not including the costs of implementing the Panel's recommendations. The Project includes three major natural gas production fields north of Inuvik and two underground natural gas pipelines (the longest is 1,220 km) to carry the gas south along the Mackenzie Valley to northern Alberta to fuel tar sands development and other uses. At the Joint Review Panel's hearings in 2007, Nature Canada argued that the full impact of the project on the lands, water and wildlife of this unique environment would leave an unacceptable footprint. If allowed to proceed, the project would:
The National Energy Board has scheduled hearings in April 2010 to hear final arguments for and against the project before making decisions (possibly by September 2010) on whether to approve the Project, and if so under what conditions. However, the Deh Cho First Nation has filed a motion in January 2010 requesting that these hearings be delayed until the federal government files its response to the Panel's recommendations. Nature Canada will be providing comments on the Joint Review Panel's Report to the National Energy Board in February. |






















